2026 Community Improvement Projects

The Village of Galena and its partners are advancing improvements to parks, streets, parking, sidewalks, stormwater infrastructure, and public facilities. Here is what residents can expect in 2026 and beyond!

01  /  4 PROJECTS

Street, Parking & Sidewalk Improvements

Target: Thanksgiving 2026

Holmes Street

McB and Sands Decker design-build team will complete widening, resurfacing, restriping and repairs as needed. Completion is planned by Thanksgiving 2026.

FundingVillage of Galena

Work byMcB and Sands Decker

Target: November 2026

Walnut Street

Improvements include street resurfacing, replacement of a stormwater catch basin, sidewalk upgrades, ADA-accessible pedestrian sidewalk, as well as an expanded, paved and striped parking area. Completion is planned for November 2026.

FundingVillage of Galena

September 15 to November 15, 2026

Columbus Street

Chemcote/CTL will install heavy-duty pavement, construct a raised center-block crosswalk and add new striping. Work is scheduled from September 15 through November 15, 2026.

Work byChemcote/CTL

Village-wide

Village-Wide Asphalt Repairs

Damaged pavement areas throughout the Village will be repaired.

02  /  3 PROJECTS

Park Improvements

Phase II underway

Miller Park Pavilion

Phase I was completed earlier in 2026. Phase II, including restrooms, electrical work, concrete, and stonework, is underway, with completion planned by Thanksgiving 2026.

Phase III, including painting, trim work, signage and landscaping, is planned for 2028.

FundingVillage of Galena

Target: November 2026

Miller Park Trail

The trail will be widened and resurfaced with completion planned for November 2026.

FundingPreservation Parks of Delaware County

Target: End of November 2026

Miller Park Parking Lot

Chemcote/CTL will pave the driveway, expand and pave the existing parking area and add striping. Completion is planned for the end of November this year.

FundingVillage of Galena

Work byChemcote/CTL

03  /  2 PROJECTS

Accessibility Improvements

Target: November 2026

Village Square Sidewalk & Crosswalk

T Crete will install new sidewalks and a crosswalk to improve ADA accessibility. Completion is planned for November 2026.

Work byT Crete

Target: December 2026

Village Hall Entrance

T Crete and Lawn Masters will construct a new ADA-accessible entrance to Village Hall. Completion is planned for December 2026.

FundingVillage of Galena

Work byT Crete and Lawn Masters

Thank you for your patience as these community improvements move forward.

Schedules are subject to weather, material availability, and construction conditions. Watch for future Village updates about timing and access.