Columbus Street, from the east side of the Middle Street/Columbus Street intersection to the west side of the Walnut Street/Columbus Street intersection, will be closed for construction per the following plan:
Construction Schedule
- Beginning Monday, October 19: traffic will be closed for construction of the stop pad. The concrete is planned to be poured by October 22 and requires five days for curing.
- Monday, October 26: milling will be performed on Columbus Street and the repair on the northbound lane of Middle Street will be completed.
- Tuesday and Wednesday, October 27-28: scheduled for new pavement.
- Thursday, October 29: scheduled for installation of the raised speed table.
The project is scheduled for completion by Sunday, November 1, weather permitting.